.下表給出了某工程各工序之間的優先關系和各工序所需時間
().畫出相應的AOE網
().列出各事件的最早發生時間最遲發生時間
().找出關鍵路徑並指明完成該工程所需最短時間【武漢交通科技大學 二 (分)】
.對圖示的AOE網絡計算各活動弧的e(ai)和l(ai)的函數值各事件(頂點)的ve(Vj)和vl (Vj)的函數值列出各條關鍵路徑【北京輕工業學院 四 (分)】
[] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] [] []